Milestones


 

Area

Description

Methodology

Timeline

4G Federation

Adding 4G Fed-Integration tests to Magma CI Dashboard

  • Defined a list of 4G Fed Integ tests (see here)
  • Adding test for HSS/OCS and PCRF
  • Started: 15/07/2022

  • Finish adding P0 tests into CI 30/09/2022

  • Finish adding P1 tests into CI 30/11/2022

5G SA Tester

  • Develop a new 5G CN tester for 5G SA (under 3-Clause BSD license)

  • 5G SA Tester repo will be hosted at OAI during the development period (then, to be decided later on)

  • Define different category of test cases for 5G

    • 5G Basic: Enable P0 tests (basic attach-detach type of test cases) on Magma CI and local dev env  (e.g., see here)

    • 5G Extended: Enable P1 tests on Magma CI and local dev env (e.g., see here)

    • 5G Federation: Add PCF tests on Magma CI (P2)

  • 5G Basic

    • Start: 01/09/2022

    • Finish: 15/01/2023 (Adding first set of test and their results in CI-Dashboard)

  • 5G Extended

    • Start: 16/01/2023

    • Finish: 30/04/2023

  • 5G Federation

    • Start: 01/05/2023

    • Finish: 31/07/2023

CI Maintenance

A continuous task to make CI green

  • CI Activity is tracked in the GitHub Issue
  • In the last few months, OAI team helped Radisys team (owner of S1AP LTE integ tests) to fix LTE Integ flakiness issues that existed for long time

    • Tracking of failures in CI

    • Analysis of failures   

    • Proposing fixes to Radisys team (either in testing scenarios or in S1AP tester)

    • From now on, OAI team is only responsible for tracking the issues, then simply flag the failures to the Radisys team

  • Worked on CWF Flakiness with TNG team

  • Starting to work on containerization of S1AP tester to make it work on ARM servers

  • It’s a continuous task-> no timeline


Agenda (Link for Google Calendar)


Agenda Item

Sub Items

Owner

Outcome/Next steps

4G Federation

@RohanRevisiting the deployment of Feg in the AGW VM for Feg-integ 

5G SA Tester

@Raphael/@Lionel
  • Lionel working on the architecture document
  • Raphael merged the proposed top-level architecture executable skeleton that will loop over the test-suite
  • Raphael synchronized our forks with upstream repositories.

CI Maintenance

@Franck/@Sagar


Meeting Recording: